Completed

P52100000045

Silver Oak · Pimpri Chinchawad (M Corp.), Pune · Anand Properties

Promised for 30 Jun 2018; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 13

Building plan5 Jun 2017View
Allotment letter7 Jun 2017View
Title report8 Jun 2017View
Form 48 Jun 2017View
Registration certificate16 Jun 2017View
OtherView
Layout planView
Building planView
Show all 13 documents
Building planView
OtherView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100000045

Is Silver Oak delayed?

MahaRERA reports it completed. Its promised completion date was 30 Jun 2018.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100000045.

Who is the promoter?

MahaRERA records Anand Properties as the promoter of P52100000045.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100000045.