P52000022089
Yash · Panvel, Raigarh · Punit Enterprises
Promised for 20 Nov 2021 — that date has passed and MahaRERA does not mark the project complete.
4 years and 11 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Risk: The latest completion date on record, 20 Nov 2021, has passed.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P52000022089
Is Yash delayed?
Yes. MahaRERA records a promised completion of 20 Nov 2021, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 0 extension certificates for P52000022089.
Who is the promoter?
MahaRERA records Punit Enterprises as the promoter of P52000022089.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52000022089.