Punit Enterprises

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ashiyana C.H.S RedevelopmentP52000007021Panvel2017Certificate Signed31 Mar 201831 Mar 2018On date
YashP52000022089Panvel2019Certificate Signed20 Nov 202120 Nov 2021On date
ParaskunjP52000053821Panvel2023Certificate Signed31 Mar 202731 Jul 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ashiyana C.H.S RedevelopmentOn date
  • YashOn date
  • Paraskunj+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Paraskunj (P52000053821).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology