RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52000020708

Mahalaxmi Enclave · Dhamote, Raigarh · Mahalaxmi Enterprises

Promised for 30 Sep 2020, extended once to 30 Mar 2022 — and that date has passed without the project marked complete on MahaRERA.

6 years and 2 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Sep 2020 to 30 Mar 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Mar 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 May 2020View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000020708

Is Mahalaxmi Enclave delayed?

Yes. MahaRERA records a promised completion of 30 Sep 2020, revised to 30 Mar 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000020708. The completion date moved from 30 Sep 2020 to 30 Mar 2022.

Who is the promoter?

MahaRERA records Mahalaxmi Enterprises as the promoter of P52000020708.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000020708.

Answers are generated from the record.

Data through7 Nov 2026, 02:43SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology