RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52000012589

Sunrise hills · Dahiwali T. Waredi, Raigarh · Samir Manohar Mantri

Promised for 25 May 2018, extended once to 30 Oct 2020 — and that date has passed without the project marked complete on MahaRERA.

8 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 25 May 2018 to 30 Oct 2020 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Oct 2020, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate4 Sep 2017View
Extension certificate18 May 2020View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000012589

Is Sunrise hills delayed?

Yes. MahaRERA records a promised completion of 25 May 2018, revised to 30 Oct 2020, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000012589. The completion date moved from 25 May 2018 to 30 Oct 2020.

Who is the promoter?

MahaRERA records Samir Manohar Mantri as the promoter of P52000012589.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000012589.

Answers are generated from the record.

Data through31 Oct 2026, 02:02SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology