RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52000010748

Malusare Residency · Warasgaon, Raigarh · Sandeep Enterprises

Promised for 9 Apr 2020, extended once to 9 Oct 2025 — and that date has passed without the project marked complete on MahaRERA.

6 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 9 Apr 2020 to 9 Oct 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 9 Oct 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate31 Aug 2017View
Extension certificate26 May 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000010748

Is Malusare Residency delayed?

Yes. MahaRERA records a promised completion of 9 Apr 2020, revised to 9 Oct 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000010748. The completion date moved from 9 Apr 2020 to 9 Oct 2025.

Who is the promoter?

MahaRERA records Sandeep Enterprises as the promoter of P52000010748.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000010748.

Answers are generated from the record.

Data through4 Nov 2026, 02:51SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology