RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52000010288

Sai Shrishti Developers · Kamothe, Raigarh · Sai Shrishti Developers

Promised for 31 Dec 2017 — that date has passed and MahaRERA does not mark the project complete.

8 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2017, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate13 Nov 2017View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000010288

Is Sai Shrishti Developers delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2017, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52000010288.

Who is the promoter?

MahaRERA records Sai Shrishti Developers as the promoter of P52000010288.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000010288.