Shree G Square · Dhamote, Raigarh · Rajesh Amarlal Thakur

Promised for 1 Mar 2018, extended once to 1 Dec 2019 — and that date has passed without the project marked complete on MahaRERA.

8 years and 8 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 1 Mar 2018 to 1 Dec 2019 (1 extension certificate on record).
  • Risk: The latest completion date on record, 1 Dec 2019, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate11 Aug 2017View
Extension certificate5 Mar 2019View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000005415

Is Shree G Square delayed?

Yes. MahaRERA records a promised completion of 1 Mar 2018, revised to 1 Dec 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000005415. The completion date moved from 1 Mar 2018 to 1 Dec 2019.

Who is the promoter?

MahaRERA records Rajesh Amarlal Thakur as the promoter of P52000005415.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000005415.