Adhiraj Samyama Tower 3B · Rohinjan, Raigarh · Adhiraj Constructions Private Limited
Promised for 30 Jun 2022, extended once to 30 Jun 2025 — and that date has passed without the project marked complete on MahaRERA.
4 years and 4 months past the original promise today.
Facts from the record. A flag is a reason to ask questions, not a verdict.
Regulatory order: PROJECT NAME:Adhiraj Samyama Tower 3B (Regulatory Case No. 173 of 2024) dated 13 March 2024.
13 Mar 2024 · matched by RERA number
View order →Yes. MahaRERA records a promised completion of 30 Jun 2022, revised to 30 Jun 2025, which has passed, and the project is not marked complete.
Deedo holds 1 extension certificate for P52000004189. The completion date moved from 30 Jun 2022 to 30 Jun 2025.
MahaRERA records Adhiraj Constructions Private Limited as the promoter of P52000004189.
1 MahaRERA order or list names P52000004189.