Adhiraj Constructions Private Limited
Company or firm · 11 projects · 11 MahaRERA registrations
11Projects11 RERA registrations
0Completedas reported on MahaRERA project pages
30%Kept RERA date3 of 10 past their proposed date, not extended
+29 moMedian delayvs RERA proposed date · 8 extended
5Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Adhiraj Samyama Tower 2BP52000003039 | Rohinjan | 2017 | Certificate Signed | 30 Jun 2021 | 10 Nov 2023 | +29 months |
| Adhiraj Samyama Tower 3BP52000004189 | Rohinjan | 2017 | Certificate Signed | 30 Jun 2022 | 30 Jun 2025 | +36 months |
| Adhiraj Samyama Tower 1AP52000004449 | Rohinjan | 2017 | Certificate Signed | 30 Jun 2022 | 30 Jun 2025 | +36 months |
| Adhiraj Samyama Tower 1BP52000004493 | Rohinjan | 2017 | Certificate Signed | 30 Jun 2022 | 30 Jun 2025 | +36 months |
| Adhiraj Samyama Tower 2AP52000007539 | Rohinjan | 2017 | Certificate Signed | 30 Jun 2021 | 10 Nov 2023 | +29 months |
| ZinniaP52000009171 | Kharghar | 2017 | Certificate Signed | 31 Jul 2018 | 31 Jul 2018 | On date |
| Adhiraj Samyama Tower 1DP52000014856 | Rohinjan | 2018 | Certificate Signed | 31 Jul 2023 | 31 Mar 2027 | +44 months |
| Adhiraj Samyama Tower 1CP52000014859 | Rohinjan | 2018 | Certificate Signed | 31 Jul 2023 | 31 Mar 2027 | +44 months |
| Adhiraj Capital City Tower OrekaP52000022907 | Rohinjan | 2019 | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | On date |
| Adhiraj Capital City Tower MerakiP52000022975 | Rohinjan | 2019 | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | On date |
| Adhiraj Capital City Tower MizaniP52000048649 | Rohinjan | 2023 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
Show all 11 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 11 registrations
Track record notes
- 3 of 10 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 44 months, for Adhiraj Samyama Tower 1D (P52000014856).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: ADHIRAJ SAMYAMA TOWER 1D (Regulatory Case No. 379 OF 2025) dated 18 June, 2025. · Adhiraj Samyama Tower 1D · P52000014856 · 18 Jun 2025
- Regulatory orderRegulatory order: PROJECT NAME: ADHIRAJ SAMYAMA TOWER 1C (Regulatory Case No. 378 OF 2025) dated 18 June, 2025. · Adhiraj Samyama Tower 1C · P52000014859 · 18 Jun 2025
- Regulatory orderRegulatory order: PROJECT NAME:Adhiraj Samyama Tower 3B (Regulatory Case No. 173 of 2024) dated 13 March 2024. · Adhiraj Samyama Tower 3B · P52000004189 · 13 Mar 2024
- Regulatory orderRegulatory order: PROJECT NAME:Adhiraj Samyama Tower 1B (Regulatory Case No. 172 of 2024) dated 13 March 2024. · Adhiraj Samyama Tower 1B · P52000004493 · 13 Mar 2024
- Regulatory orderRegulatory order: PROJECT NAME:Adhiraj Samyama Tower 1A (Regulatory Case No. 171 of 2024) dated 13 March 2024. · Adhiraj Samyama Tower 1A · P52000004449 · 13 Mar 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology