RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52000003264

Tulsi Chhaya · Diksal, Raigarh · Tulsi Unison

Promised for 25 Dec 2019, extended once to 24 Jun 2023 — and that date has passed without the project marked complete on MahaRERA.

6 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 25 Dec 2019 to 24 Jun 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 24 Jun 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate5 Aug 2017View
Extension certificate8 Sep 2021View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52000003264

Is Tulsi Chhaya delayed?

Yes. MahaRERA records a promised completion of 25 Dec 2019, revised to 24 Jun 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000003264. The completion date moved from 25 Dec 2019 to 24 Jun 2023.

Who is the promoter?

MahaRERA records Tulsi Unison as the promoter of P52000003264.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000003264.

Answers are generated from the record.

Data through9 Nov 2026, 01:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology