Adhiraj Samyama Tower 2B · Rohinjan, Raigarh · Adhiraj Constructions Private Limited

Promised for 30 Jun 2021, extended once to 10 Nov 2023 — and that date has passed without the project marked complete on MahaRERA.

5 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2021 to 10 Nov 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 10 Nov 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate18 May 2020View
Extension certificate27 Dec 2023View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52000003039

Is Adhiraj Samyama Tower 2B delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2021, revised to 10 Nov 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000003039. The completion date moved from 30 Jun 2021 to 10 Nov 2023.

Who is the promoter?

MahaRERA records Adhiraj Constructions Private Limited as the promoter of P52000003039.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000003039.