RegisteredExtendedMahaRERA status: Certificate Signed

P51900080218

Runwal Raaya · Worli, Mumbai City · Aethon Developers Private Limited

Promised for 31 Dec 2032, extended to 30 Apr 2033, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2032 to 30 Apr 2033.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate14 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51900080218

Is Runwal Raaya delayed?

Its completion moved from 31 Dec 2032 to 30 Apr 2033; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51900080218. The completion date moved from 31 Dec 2032 to 30 Apr 2033.

Who is the promoter?

MahaRERA records Aethon Developers Private Limited as the promoter of P51900080218.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51900080218.

Answers are generated from the record.

Data through9 Nov 2026, 02:55SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology