Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered1 extensionMahaRERA status: Certificate Signed

P51900047971

T - Square · Mumbai City · Trinetra Builders And Developers

Promised for 31 Mar 2025, extended once to 31 Mar 2027, which is still ahead.

The revised date is 2 years after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2025 to 31 Mar 2027 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate2 Dec 2022View
Extension certificate10 Jun 2025View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51900047971

Is T - Square delayed?

Its completion moved from 31 Mar 2025 to 31 Mar 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P51900047971. The completion date moved from 31 Mar 2025 to 31 Mar 2027.

Who is the promoter?

MahaRERA records Trinetra Builders And Developers as the promoter of P51900047971.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51900047971.

Answers are generated from the record.

Data through4 Nov 2026, 02:04SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology