Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered1 extensionMahaRERA status: Certificate Signed

P51900033836

Cynthiandra · Mumbai City · Shubh Laxmi Developers

Promised for 31 Dec 2025, extended once to 30 Dec 2026, which is still ahead.

The revised date is 1 year after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2025 to 30 Dec 2026 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate8 Mar 2022View
Extension certificate28 Aug 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51900033836

Is Cynthiandra delayed?

Its completion moved from 31 Dec 2025 to 30 Dec 2026; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P51900033836. The completion date moved from 31 Dec 2025 to 30 Dec 2026.

Who is the promoter?

MahaRERA records Shubh Laxmi Developers as the promoter of P51900033836.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51900033836.

Answers are generated from the record.

Data through30 Oct 2026, 02:39SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology