RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51900032290

Eklavya House · Mumbai City · Aikya Realty Pvt Ltd

Promised for 30 Dec 2023, extended once to 25 Jun 2024 — and that date has passed without the project marked complete on MahaRERA.

2 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2023 to 25 Jun 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 25 Jun 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate22 Dec 2021View
Extension certificate1 Jul 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51900032290

Is Eklavya House delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2023, revised to 25 Jun 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51900032290. The completion date moved from 30 Dec 2023 to 25 Jun 2024.

Who is the promoter?

MahaRERA records Aikya Realty Pvt Ltd as the promoter of P51900032290.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51900032290.

Answers are generated from the record.

Data through4 Nov 2026, 02:14SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology