RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51900031688
Meraki · Mumbai City · Amrut Realtors Private Limited
Promised for 31 Mar 2025, extended once to 31 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.
1 year and 8 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Mar 2025 to 31 Dec 2025 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Dec 2025, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51900031688
Is Meraki delayed?
Yes. MahaRERA records a promised completion of 31 Mar 2025, revised to 31 Dec 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51900031688. The completion date moved from 31 Mar 2025 to 31 Dec 2025.
Who is the promoter?
MahaRERA records Amrut Realtors Private Limited as the promoter of P51900031688.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51900031688.