P51900008466
One India Tower · Others, Mumbai City · One India Constructions Private Limited
Promised for 30 Dec 2028, extended to 30 Apr 2029, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2028 to 30 Apr 2029.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51900008466
Is One India Tower delayed?
Its completion moved from 30 Dec 2028 to 30 Apr 2029; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P51900008466. The completion date moved from 30 Dec 2028 to 30 Apr 2029.
Who is the promoter?
MahaRERA records One India Constructions Private Limited as the promoter of P51900008466.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51900008466.