Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P51800079370

Mpr Varsha · Dahisar, Mumbai Suburban · Mpr Group

Promised for 1 Oct 2027, extended to 1 Feb 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 1 Oct 2027 to 1 Feb 2028.

Documents 1

Registration certificate3 Mar 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800079370

Is Mpr Varsha delayed?

Its completion moved from 1 Oct 2027 to 1 Feb 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800079370. The completion date moved from 1 Oct 2027 to 1 Feb 2028.

Who is the promoter?

MahaRERA records Mpr Group as the promoter of P51800079370.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800079370.

Answers are generated from the record.

Data through23 Oct 2026, 02:20SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology