Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%1 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mpr Mahavir DarshanP51800053758Dahisar2023Not reported1 Jul 2026—On date
Mpr NileshP51800056192Dahisar2024Not reported11 Jan 2027—On date
Mpr VarshaP51800079370Dahisar2025Not reported1 Oct 2027—On date
Mpr Shri Paras DarshanP51800080359Valnai2025Not reported1 Feb 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mpr Mahavir DarshanOn date
  • Mpr NileshOn date
  • Mpr VarshaOn date
  • Mpr Shri Paras DarshanOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.