Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51800077645

Perry Apartment · Valnai, Mumbai Suburban · Pankaj Shantilal Parikh

Promised for 31 Dec 2025 — that date has passed and MahaRERA does not mark the project complete.

11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2025, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate17 Oct 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800077645

Is Perry Apartment delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800077645.

Who is the promoter?

MahaRERA records Pankaj Shantilal Parikh as the promoter of P51800077645.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800077645.

Answers are generated from the record.

Data through4 Nov 2026, 01:54SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology