RegisteredExtendedMahaRERA status: Certificate Signed

P51800066488

Avyukta Vedant · Borivali, Mumbai Suburban · Shivoham Infrahomes Llp

Promised for 31 Mar 2029, extended to 31 Jul 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2029 to 31 Jul 2029.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate11 Jun 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800066488

Is Avyukta Vedant delayed?

Its completion moved from 31 Mar 2029 to 31 Jul 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800066488. The completion date moved from 31 Mar 2029 to 31 Jul 2029.

Who is the promoter?

MahaRERA records Shivoham Infrahomes Llp as the promoter of P51800066488.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800066488.