Shivoham Infrahomes Llp

Deedo IDDD-SEJ3

Of 3 registrations whose promised date has arrived, 3 kept it (100%).

Projects88 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

4 registrations of 8 ran past the RERA date

Months late against the original RERA promise, per registration

8 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Avyukta RajhansP51800030322BorivaliCertificate Signed31 Dec 202431 Dec 2024On date
Avyukta GoculP51800045317AndheriCertificate Signed31 Dec 202431 Dec 2024On date
Avyukta PrakashP51800052786BorivaliCertificate Signed31 Dec 202531 Dec 2025On date
Avyukta VedantP51800066488BorivaliCertificate Signed31 Mar 202931 Jul 2029+4 mo
Avyukta JayeshPM1180002500769BorivaliCertificate Signed31 Mar 202931 Jul 2029+4 mo
Avyukta ParijatP51800081115EksarCertificate Signed31 Mar 203031 Jul 2030+4 mo
Avyukta Jay AbhilashaPM1180002601013BorivaliCertificate Signed30 Jun 202930 Oct 2029+4 mo
Avyukta TattvaPM1180002602283KanheriNot on record31 Dec 2030—On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology