Sajay Avenue 18 · Bandra, Mumbai Suburban · Vinca Realtors Private Limited
Promised for 31 Aug 2026 — that date has passed and MahaRERA does not mark the project complete.
3 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Risk: The latest completion date on record, 31 Aug 2026, has passed.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51800053190
Is Sajay Avenue 18 delayed?
Yes. MahaRERA records a promised completion of 31 Aug 2026, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 0 extension certificates for P51800053190.
Who is the promoter?
MahaRERA records Vinca Realtors Private Limited as the promoter of P51800053190.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800053190.