RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51800050904
5th Element · Andheri, Mumbai Suburban · Pratham Varadvinayak Builders And Developers Private Limited
Promised for 30 Jun 2028, extended once to 30 Oct 2028, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2028 to 30 Oct 2028 (1 extension certificate on record).
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51800050904
Is 5th Element delayed?
Its completion moved from 30 Jun 2028 to 30 Oct 2028; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 1 extension certificate for P51800050904. The completion date moved from 30 Jun 2028 to 30 Oct 2028.
Who is the promoter?
MahaRERA records Pratham Varadvinayak Builders And Developers Private Limited as the promoter of P51800050904.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800050904.
Answers are generated from the record.
