Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered1 extensionMahaRERA status: Certificate Signed

P51800047778

Sla Avenue · Andheri, Mumbai Suburban · Samarth Leela Associates

Promised for 31 Dec 2027, extended once to 30 Apr 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2027 to 30 Apr 2028 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Extension certificate14 Aug 2026View
Registration certificate20 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800047778

Is Sla Avenue delayed?

Its completion moved from 31 Dec 2027 to 30 Apr 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800047778. The completion date moved from 31 Dec 2027 to 30 Apr 2028.

Who is the promoter?

MahaRERA records Samarth Leela Associates as the promoter of P51800047778.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800047778.

Answers are generated from the record.

Data through9 Nov 2026, 02:54SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology