Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800045589

Cassias · Andheri, Mumbai Suburban · Sdc Infrastructure Pvt Ltd

Promised for 30 Jun 2024, extended once to 31 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

2 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2024 to 31 Dec 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate24 May 2022View
Extension certificate22 Jul 2024View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51800045589

Is Cassias delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2024, revised to 31 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800045589. The completion date moved from 30 Jun 2024 to 31 Dec 2024.

Who is the promoter?

MahaRERA records Sdc Infrastructure Pvt Ltd as the promoter of P51800045589.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800045589.

Answers are generated from the record.

Data through3 Nov 2026, 02:12SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology