RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51800033931

Supreme Evana · Andheri, Mumbai Suburban · Supreme Mega Constructions Llp

Promised for 30 Jun 2024 — that date has passed and MahaRERA does not mark the project complete.

2 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Jun 2024, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate14 Mar 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800033931

Is Supreme Evana delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800033931.

Who is the promoter?

MahaRERA records Supreme Mega Constructions Llp as the promoter of P51800033931.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800033931.