Kings Pride · Kurla, Mumbai Suburban · Nilesh Laxmikant Kudalkar
Promised for 30 Dec 2023, extended once to 29 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.
2 years and 11 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2023 to 29 Dec 2024 (1 extension certificate on record).
- !Risk: The latest completion date on record, 29 Dec 2024, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 3
Orders 0
No MahaRERA order or list names this number.
Questions about P51800023958
Is Kings Pride delayed?
Yes. MahaRERA records a promised completion of 30 Dec 2023, revised to 29 Dec 2024, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51800023958. The completion date moved from 30 Dec 2023 to 29 Dec 2024.
Who is the promoter?
MahaRERA records Nilesh Laxmikant Kudalkar as the promoter of P51800023958.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800023958.
Answers are generated from the record.