RegisteredRevised date passed1 extensionMahaRERA status: Lapsed

P51800020573

Arya Greens · Kurla, Mumbai Suburban · Anushka Developers

Promised for 30 Dec 2023, extended once to 30 Jun 2025 — and that date has passed without the project marked complete on MahaRERA.

2 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2023 to 30 Jun 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2025, has passed.
  • Caution: 4 other MahaRERA orders name this registration.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 87

Title report11 Apr 2019View
Commencement certificate11 Apr 2019View
Form B11 Apr 2019View
Form 111 Apr 2019View
Form 211 Apr 2019View
Allotment letter11 Apr 2019View
Commencement certificate17 Oct 2020View
Registration certificate9 Sep 2021View
Show all 87 documents
Encumbrance details17 Jan 2024View
Commencement certificate17 Jan 2024View
Commencement certificate17 Jan 2024View
Form B17 Jan 2024View
Form 117 Jan 2024View
Form 117 Jan 2024View
Form 117 Jan 2024View
Form 117 Jan 2024View
Form 117 Jan 2024View
Form 117 Jan 2024View
Form 117 Jan 2024View
Form 117 Jan 2024View
Form 117 Jan 2024View
Form 117 Jan 2024View
Form 117 Jan 2024View
Form 217 Jan 2024View
Form 217 Jan 2024View
Form 217 Jan 2024View
Form 217 Jan 2024View
Form 217 Jan 2024View
Form 217 Jan 2024View
Form 217 Jan 2024View
Form 217 Jan 2024View
Form 217 Jan 2024View
Form 217 Jan 2024View
Form 217 Jan 2024View
Form 2A17 Jan 2024View
Form 2A17 Jan 2024View
Form 2A17 Jan 2024View
Form 2A17 Jan 2024View
Other17 Jan 2024View
Other17 Jan 2024View
Other17 Jan 2024View
Encumbrance details17 Jan 2024View
Allotment letter17 Jan 2024View
Other17 Jan 2024View
Form B18 Jan 2024View
Form 518 Jan 2024View
Form 518 Jan 2024View
Form 518 Jan 2024View
Form 518 Jan 2024View
Commencement certificate13 Jun 2024View
Form 123 Dec 2024View
Form 123 Dec 2024View
Form 123 Dec 2024View
Form 223 Dec 2024View
Form 223 Dec 2024View
Form 223 Dec 2024View
Other23 Dec 2024View
Commencement certificate23 Dec 2024View
Form 2A23 Dec 2024View
Form B24 Dec 2024View
Form 513 Jan 2025View
Extension certificate3 Feb 2025View
OtherView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Building planView
Building planView
Building planView
Allotment letterView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 4

Questions about P51800020573

Is Arya Greens delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2023, revised to 30 Jun 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800020573. The completion date moved from 30 Dec 2023 to 30 Jun 2025.

Who is the promoter?

MahaRERA records Anushka Developers as the promoter of P51800020573.

Is it on any MahaRERA regulatory list?

4 MahaRERA orders or lists name P51800020573.

Answers are generated from the record.

Data through30 Oct 2026, 02:18SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology