Company or firm · first RERA registration 2019

Anushka Developers

Deedo IDDD-KQM2

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 34 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay34 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases4no insolvency

1 registration of 1 ran past the RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
complaintArya GreensComplaint CC006000000196720Not on record
complaintArya GreensComplaint CC006000000261959Not on record
complaintArya GreensComplaint CC12503461Not on record
complaintArya GreensComplaint CC12504577Not on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Arya GreensP51800020573KurlaLapsed30 Dec 202330 Jun 2025+34 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology