RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800020334

Sparkle 9 · Borivali, Mumbai Suburban · Sparkle Earth Developer

Promised for 30 Mar 2023, extended once to 23 Jul 2024 — and that date has passed without the project marked complete on MahaRERA.

3 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Mar 2023 to 23 Jul 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 23 Jul 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
Extension certificate17 Mar 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800020334

Is Sparkle 9 delayed?

Yes. MahaRERA records a promised completion of 30 Mar 2023, revised to 23 Jul 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800020334. The completion date moved from 30 Mar 2023 to 23 Jul 2024.

Who is the promoter?

MahaRERA records Sparkle Earth Developer as the promoter of P51800020334.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800020334.

Answers are generated from the record.

Data through29 Oct 2026, 02:07SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology