Sparkle Earth Developer

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sparkle 9P51800020334Borivali2019Not reported30 Mar 202323 Jul 2024+16 months
Sparkle UmadarshanP51800051376Borivali2023Certificate Signed31 Dec 202631 Dec 2026On date
Sparkles Mitali Business CentreP51800055085Malad2024Not reported5 Apr 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sparkle 9+16 mo
  • Sparkle UmadarshanOn date
  • Sparkles Mitali Business CentreOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 16 months, for Sparkle 9 (P51800020334).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology