Shreejee Mrugarchana Chs Ltd · Kurla, Mumbai Suburban · Shreejee Buildcon Homes Llp
Promised for 30 Mar 2023, extended once to 31 Jul 2025 — and that date has passed without the project marked complete on MahaRERA.
3 years and 8 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Mar 2023 to 31 Jul 2025 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Jul 2025, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51800020300
Is Shreejee Mrugarchana Chs Ltd delayed?
Yes. MahaRERA records a promised completion of 30 Mar 2023, revised to 31 Jul 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51800020300. The completion date moved from 30 Mar 2023 to 31 Jul 2025.
Who is the promoter?
MahaRERA records Shreejee Buildcon Homes Llp as the promoter of P51800020300.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800020300.