Sana Arcade · Kurla, Mumbai Suburban · Kadri Construction Co
Promised for 1 Jan 2019, extended once to 31 Dec 2019 — and that date has passed without the project marked complete on MahaRERA.
7 years and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 1 Jan 2019 to 31 Dec 2019 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Dec 2019, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51800012722
Is Sana Arcade delayed?
Yes. MahaRERA records a promised completion of 1 Jan 2019, revised to 31 Dec 2019, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51800012722. The completion date moved from 1 Jan 2019 to 31 Dec 2019.
Who is the promoter?
MahaRERA records Kadri Construction Co as the promoter of P51800012722.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800012722.