RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800011529

New Bhagyashree Chs Ltd · Andheri, Mumbai Suburban · K. Anand Construction Private Limited

Promised for 31 Dec 2017, extended once to 28 Feb 2018 — and that date has passed without the project marked complete on MahaRERA.

8 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2017 to 28 Feb 2018 (1 extension certificate on record).
  • Risk: The latest completion date on record, 28 Feb 2018, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate13 Nov 2017View
Extension certificate1 Jul 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800011529

Is New Bhagyashree Chs Ltd delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2017, revised to 28 Feb 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800011529. The completion date moved from 31 Dec 2017 to 28 Feb 2018.

Who is the promoter?

MahaRERA records K. Anand Construction Private Limited as the promoter of P51800011529.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800011529.

Answers are generated from the record.