Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51800010505

Pearl Palace · Andheri, Mumbai Suburban · Chandiwala Enterprises

Promised for 30 Dec 2021 — that date has passed and MahaRERA does not mark the project complete.

4 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Dec 2021, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800010505

Is Pearl Palace delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800010505.

Who is the promoter?

MahaRERA records Chandiwala Enterprises as the promoter of P51800010505.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800010505.

Answers are generated from the record.

Data through30 Oct 2026, 02:02SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology