Chandiwala Enterprises

Company or firm · 10 projects · 12 MahaRERA registrations

10Projects12 RERA registrations
0Completedas reported on MahaRERA project pages
83%Kept RERA date5 of 6 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Brooklyn ParkP99000002745Dongare2017Certificate Signed10 Jul 202510 Jul 2025On date
Pearl HazelineP51800003301Andheri2017Certificate Signed31 May 201831 May 2018On date
Pearl HarmonyP51800004224Andheri2017Certificate Signed30 Dec 202130 Dec 2023+24 months
Pearl PlatinumP51800004462Andheri2017Certificate Signed30 Dec 202330 Dec 2023On date
Pearl PalaceP51800010505Andheri2017Certificate Signed30 Dec 202130 Dec 2021On date
Pearl MajesticP51800015348Andheri2018Certificate Signed30 Dec 202330 Dec 2023On date
Pearl HeavenP51800029797Andheri2021Certificate Signed31 Dec 202631 Dec 2026On date
Pearl HeavenP51800049464Andheri2023Certificate Signed31 Dec 202731 Dec 2027On date
Pearl Platinum A WingP51800049549Oshiwara2023Certificate Signed31 Dec 202830 Apr 2029+4 months
Pearl BlessingsP51800054883Kondivita2024Certificate Signed31 Dec 202830 Apr 2029+4 months
Pearl Platinum Wing BP51800055438Oshiwara2024Certificate Signed31 Dec 202830 Apr 2029+4 months
Pearl HeavenPR1182022501055Andheri2025Certificate Signed31 Dec 202730 Apr 2028+4 months
Show all 12 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Brooklyn ParkOn date
  • Pearl HazelineOn date
  • Pearl Harmony+24 mo
  • Pearl PlatinumOn date
  • Pearl PalaceOn date
  • Pearl MajesticOn date
  • Pearl HeavenOn date
  • Pearl HeavenOn date
  • Pearl Platinum A Wing+4 mo
  • Pearl Blessings+4 mo
Show all 12 registrations
  • Pearl Platinum Wing B+4 mo
  • Pearl Heaven+4 mo

Track record notes

  • 5 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Pearl Harmony (P51800004224).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology