RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800009358

Maya Harmony · Kurla, Mumbai Suburban · Maya Developers

Promised for 20 Nov 2020, extended once to 31 Mar 2024 — and that date has passed without the project marked complete on MahaRERA.

6 years past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 20 Nov 2020 to 31 Mar 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Mar 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate18 May 2020View
Extension certificate27 Dec 2023View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51800009358

Is Maya Harmony delayed?

Yes. MahaRERA records a promised completion of 20 Nov 2020, revised to 31 Mar 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800009358. The completion date moved from 20 Nov 2020 to 31 Mar 2024.

Who is the promoter?

MahaRERA records Maya Developers as the promoter of P51800009358.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800009358.

Answers are generated from the record.