Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800007837

Madhukunj · Borivali, Mumbai Suburban · Dhara Construction

Promised for 31 Mar 2018, extended once to 31 Jul 2018 — and that date has passed without the project marked complete on MahaRERA.

8 years and 8 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2018 to 31 Jul 2018 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Jul 2018, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 Aug 2017View
Extension certificate10 Apr 2018View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800007837

Is Madhukunj delayed?

Yes. MahaRERA records a promised completion of 31 Mar 2018, revised to 31 Jul 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800007837. The completion date moved from 31 Mar 2018 to 31 Jul 2018.

Who is the promoter?

MahaRERA records Dhara Construction as the promoter of P51800007837.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800007837.

Answers are generated from the record.

Data through3 Nov 2026, 01:45SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology