RegisteredExtendedMahaRERA status: Certificate Signed

P51800005832

Linkpark · Borivali, Mumbai Suburban · Adarsh Industrial Estate Private Limited

Promised for 19 Oct 2026, extended to 19 Feb 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 19 Oct 2026 to 19 Feb 2027.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800005832

Is Linkpark delayed?

Its completion moved from 19 Oct 2026 to 19 Feb 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800005832. The completion date moved from 19 Oct 2026 to 19 Feb 2027.

Who is the promoter?

MahaRERA records Adarsh Industrial Estate Private Limited as the promoter of P51800005832.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800005832.