RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51800004821

Aditya Enterprises · Borivali, Mumbai Suburban · Aditya Enterprise

Promised for 30 Jun 2021 — that date has passed and MahaRERA does not mark the project complete.

5 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Jun 2021, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 May 2020View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51800004821

Is Aditya Enterprises delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800004821.

Who is the promoter?

MahaRERA records Aditya Enterprise as the promoter of P51800004821.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800004821.

Answers are generated from the record.

Data through9 Nov 2026, 01:51SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology