Registered1 extensionMahaRERA status: Certificate Signed

P51800003722

Maithili Residency · Kurla, Mumbai Suburban · Global Oricon Developers

Promised for 31 Dec 2019, extended once to 31 Dec 2027, which is still ahead.

The revised date is 8 years after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2019 to 31 Dec 2027 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate6 Aug 2017View
Extension certificate4 Dec 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800003722

Is Maithili Residency delayed?

Its completion moved from 31 Dec 2019 to 31 Dec 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800003722. The completion date moved from 31 Dec 2019 to 31 Dec 2027.

Who is the promoter?

MahaRERA records Global Oricon Developers as the promoter of P51800003722.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800003722.

Answers are generated from the record.

Data through25 Oct 2026, 02:03SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology