Company or firm · first RERA registration 2017
Global Oricon Developers
Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 66 mo — longer than Maharashtra's 4 mo.
Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay66 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Maithili ResidencyP51800003722 | Kurla | Certificate Signed | 31 Dec 2019 | 31 Dec 2027 | +96 mo |
| Maithili ResidencyP51800008465 | Kurla | Certificate Signed | 31 Dec 2024 | 31 Dec 2027 | +36 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology