Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800002979

East Point · Kurla, Mumbai Suburban · Vital Developers Pvt. Ltd

Promised for 31 Jan 2020, extended once to 31 Jul 2022 — and that date has passed without the project marked complete on MahaRERA.

6 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Jan 2020 to 31 Jul 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Jul 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate4 Aug 2017View
Extension certificate30 Mar 2022View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51800002979

Is East Point delayed?

Yes. MahaRERA records a promised completion of 31 Jan 2020, revised to 31 Jul 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800002979. The completion date moved from 31 Jan 2020 to 31 Jul 2022.

Who is the promoter?

MahaRERA records Vital Developers Pvt. Ltd as the promoter of P51800002979.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800002979.

Answers are generated from the record.

Data through3 Nov 2026, 01:41SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology