Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800001724

Primo · Kurla, Mumbai Suburban · Ceear Land Developers Llp

Promised for 30 Jun 2021, extended once to 30 Sep 2026 — and that date has passed without the project marked complete on MahaRERA.

5 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2021 to 30 Sep 2026 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Sep 2026, has passed.
  • Caution: 1 other MahaRERA order names this registration.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 May 2020View
Extension certificate17 Feb 2026View

Orders 1

Regulatory order

Regulatory order: PROJECT NAME: PRIMO (Regulatory Case No. 10 of 2023) dated 03 May 2023.

24 Mar 2023 · matched by RERA number

View order →

Questions about P51800001724

Is Primo delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2021, revised to 30 Sep 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800001724. The completion date moved from 30 Jun 2021 to 30 Sep 2026.

Who is the promoter?

MahaRERA records Ceear Land Developers Llp as the promoter of P51800001724.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P51800001724.

Answers are generated from the record.

Data through31 Oct 2026, 01:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology