Atmosphere Phase 1 · Kurla, Mumbai Suburban · Atmosphere Realty Pvt Ltd
Promised for 31 Oct 2019 — that date has passed and MahaRERA does not mark the project complete.
7 years and 1 month past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Risk: The latest completion date on record, 31 Oct 2019, has passed.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51800001243
Is Atmosphere Phase 1 delayed?
Yes. MahaRERA records a promised completion of 31 Oct 2019, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 0 extension certificates for P51800001243.
Who is the promoter?
MahaRERA records Atmosphere Realty Pvt Ltd as the promoter of P51800001243.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800001243.