RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51800001144
Park Royale · Andheri, Mumbai Suburban · Shivranjani Properties Llp
Promised for 30 Dec 2021, extended once to 30 Dec 2022 — and that date has passed without the project marked complete on MahaRERA.
4 years and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2021 to 30 Dec 2022 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Dec 2022, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51800001144
Is Park Royale delayed?
Yes. MahaRERA records a promised completion of 30 Dec 2021, revised to 30 Dec 2022, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51800001144. The completion date moved from 30 Dec 2021 to 30 Dec 2022.
Who is the promoter?
MahaRERA records Shivranjani Properties Llp as the promoter of P51800001144.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800001144.
Answers are generated from the record.