Skip to content
Deedo home
Menu

Park Royale

Completion due Dec 2026

Andheri, Mumbai Suburban 400059 |Promoter: Shivranjani Properties LLP

26 Jul 2017Registered with MahaRERAFirst of 2 registrations
31 Dec 2026Promised completionLatest across registrations
30 Dec 2022Revised completion1 of 2 registrations pushed back, by up to 1 year
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.12258, 72.88587
Park Royale is at latitude 19.12258, longitude 72.88587.

Also registered as

Park Royale C D WingPark Royale Phase III
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

P51800001144

The latest completion date on record passed 3 years and 10 months ago.

Registered
26 Jul 2017
Promised
30 Dec 2021
Revised
30 Dec 2022

Completion promised for 31 Dec 2026

P51800053602
Registered
10 Nov 2023
Promised
31 Dec 2026

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5180000114426 Jul 201730 Dec 202130 Dec 2022Shivranjani Properties LLPProject page
P5180005360210 Nov 202331 Dec 2026—Shivranjani Properties LLPProject page

Documents

3 documents held by Deedo

Registration certificates

  • Registration certificateP51800001144 · 9 Sep 2021ViewSource
  • Registration certificateP51800053602 · 10 Nov 2023ViewSource

Extension certificate

  • Extension certificateP51800001144 · 10 Jan 2022ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Andheri

Survey, CTS, gat or plot numbers

12412412512512612678S. No. 16 Hissa 11

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology