RegisteredExtendedMahaRERA status: Certificate Signed

P51700055145

Midtown Adam · Adharwadi, Thane · Moon Star Developers LLP

Promised for 31 Jul 2027, extended to 30 Nov 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Jul 2027 to 30 Nov 2027.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate4 Mar 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700055145

Is Midtown Adam delayed?

Its completion moved from 31 Jul 2027 to 30 Nov 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700055145. The completion date moved from 31 Jul 2027 to 30 Nov 2027.

Who is the promoter?

MahaRERA records Moon Star Developers LLP as the promoter of P51700055145.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700055145.